Pre- Installation of Flyover connecting Baladaksha Mw; & Chittampalama Gardiner Mw; over railway track & Beira Lake in Slave Island.

Contract Number     :           DM-0743

Employer                    :           Dockyard General Engineering Services (Pvt) Ltd.

Contractor                  :           M/S Sevon Engineering (Pvt) Ltd.

Consultant                  :           Road Development Authority.

Date of Award            :           2022.02.01

Date of Completion  :           2022.08.09

Contract Period          :           189 Days

Contract Value            :           Rs. 41,952,400.00 + VAT

 

Brief description of the project is as follows.

The steel bridge was imported from the country of Span and designed by “CENTUNION”. The bridge consists of 6 spans which are 266.6 meters long and 9.0 meters wide.

The purpose of pre-installation is to ensure that the fabricated steel members are in accordance with the design parameters before installing the original location. If any deviation is found, necessary modification was done and corrected as necessary before dispatch from the yard.

This project was mainly dependent on the capacity of the heavy machinery such as mobile crane, trailers and also technical personnel with high accuracy of leveling.