Land Development Work for Proposed BMF Warehouse for Martin Bauer Hayleys (Pvt) Ltd at Dickoya.
Employer : Martin Bauer Hayleys (Pvt) Ltd.
Consultant : Hayleys Project Consultant PLC.
Contractor : Sevon Engineering (Pvt) Ltd.
Scope of Work : Bulk Excavation of existing ground to reduce level, Gabion Wall Constructions, Rock blasting & Soil filling & compaction up to proposed formation level.
Date of Award : 2020.03.11
Date of Completion : 2020.07.23
Contract Period : 134 Days
Contract Value : Rs. 32,688,995.23 + VAT
The summary of the project is as follows.
The bulk excavation is done to reduce the existing ground level for construction of the proposed warehouse building. Also filling of lower levels up to the proposed formation level was done by using excavated soil & compacted with a vibrating roller.
We had to face an unexpected situation while excavation was ongoing; a huge rock layer was found which had more volume than estimated by the consultant. So, project duration was extended due to this and also we had to deploy higher capacity machinery (excavator, breaker) than we had planned.
The Gabion wall and boulder packing was constructed as an earth retaining structure at the embankment end.